New Romania–Moldova Bridge to Cost Nearly €100 Million: Trucks Could Finally Bypass the Reservoir Dam Crossing

A new bridge will allow trucks to cross the border between Romania and the Republic of Moldova without using the road along the Costesti-Stanca reservoir dam. The project includes a 170-metre bridge, a 5.73-kilometre access road and a modern customs checkpoint with six inspection gates in each direction. The preliminary cost of construction works is close to half a billion Romanian lei, BANI.MD reports.

According to environmental documentation reviewed by APIX.ro, Romania’s National Company for Road Infrastructure Management (CNAIR) is preparing an investment project in Botosani County. However, most of the new road connection will be built on the territory of the Republic of Moldova.

Currently, traffic across the border at the Stanca-Costesti crossing takes place along the reservoir dam. For safety reasons, the movement and stopping of trucks are restricted, contributing to congestion at the border checkpoint.

The new bridge will be located south of the existing crossing. The customs infrastructure will include dedicated lanes for trucks, allowing goods to be transported more efficiently between the two countries.

Under the project, the new road on the Romanian side will branch off from national road DN24C via a roundabout located approximately 300 metres from Stanca, a locality within the town of Stefanesti.

The road will then run for approximately 1.7 kilometres to the border, cross the Prut River and continue for another four kilometres through the Republic of Moldova, where it will connect to regional road R7.

Initially, the road will have one lane in each direction. However, the designers propose reserving land to allow for its potential expansion into an expressway.

Two bridge construction options

The feasibility study outlines two possible designs for the bridge.

The first option involves metal girders and a concrete deck. Construction and installation costs are estimated at 477.1 million Romanian lei, excluding VAT.

The second option предусматривает a concrete structure, with costs estimated at approximately 480.8 million Romanian lei.

These figures cover only construction and installation works. The total investment cost will be determined at a later stage.

As for the implementation schedule, the designers estimate six months for preparing the technical design and obtaining the necessary permits, followed by another 24 months for construction.

These timelines are preliminary, and no exact date for the start of construction has been announced.